Renovations

Full home renovation: where to start the quote

Quoting a full renovation in a disorderly way leads to expensive mistakes. Recommended order of items and trades so nothing is left out.

PT
PresupuestoYa Team
27 July 2026 · 1 min read

A full renovation involves several trades working in a specific order, and quoting it without following that logical order is the most common reason cost overruns appear mid-job.

Demolition and structure phase

It all starts by demolishing what isn't kept (partitions, tiling, old installations) and, if the project requires, working on the structure (opening gaps, reinforcements). This phase must be quoted with a margin, because it's where hidden surprises tend to appear after demolishing.

Installations before closing up

Electrics, plumbing and air conditioning are installed with partitions and floors still open, before any finish. Quoting this phase completely avoids having to re-chip finished finishes to correct an oversight.

Finishes: from the inside out

Tiling and flooring come before painting, and painting before the final joinery (doors, skirting), so as not to damage elements already installed during later, messier phases. The order matters as much as the items themselves.

Why a phased quote makes everything easier

Breaking the quote down following this work order, instead of a single overall price, helps the client understand the process and makes it easier to adjust the scope of the renovation in phases if the total quote exceeds expectations.

Need to quote a complete full renovation? Do it in PresupuestoYa.

Share

Want to calculate this quote automatically?

PresupuestoYa calculates materials, quantities and total cost in minutes, for this and 19 other trades.

Create a free quote →