How much does a bricklayer charge per hour in Spain and how much do they get done in a day?

Average hourly rate of a skilled bricklayer and labourer, how many m² of floor tile or wall tiling are laid per day and what waste management to include in the quote.

PT
PresupuestoYa Team
22 July 2026 · 2 min read

Working out how long a masonry job will take isn't just a matter of hourly price: it's understanding the real output of a skilled worker under normal conditions, so as not to commit to a deadline that then isn't met.

How much a masonry hour costs in Spain

The hourly rate of a skilled bricklayer ranges €18–30/h, and that of a labourer €12–18/h depending on the area. For a complete skilled worker + labourer rate, add both.

How much a skilled worker gets done in a day

As a planning reference: a skilled bricklayer can lay about 8–10 m²/day of floor tiles under normal conditions, or tile 6–8 m²/day of wall. Preparing the substrate can add 1–2 more days before starting to lay the material.

These numbers serve to calculate realistic timescales before committing to the client, not just to quote hours.

Combining skilled worker and labourer

Combining skilled worker + labourer lets you progress faster on demolition, carrying rubble or preparing mortar without pricing the whole day at the skilled rate — the labourer takes on the tasks that don't require their specific qualification.

Travel and waste management

  • Travel: if charged per kilometre, the typical price in Spain is €0.30–0.50/km, to cover fuel and wear on the vehicle — especially relevant if material or rubble is also carried on each trip.
  • Waste management (certificate): on larger jobs, the town council or the owners' association may require a construction and demolition waste (RCD) treatment certificate through an authorised handler. Include it as a separate item when the disposal is handled directly, not just the skip hire.

Frequently asked questions

How long does a skilled worker take to tile a 6 m² bathroom? About a day, according to the standard output of 6–8 m²/day, not counting the prior preparation of the substrate if needed.

How much does a labourer charge compared with a skilled bricklayer? €12–18/h the labourer, against €18–30/h the skilled worker, depending on the area.

Is the waste management certificate mandatory? Not always, but on larger jobs the town council or the community may require it — it's worth checking before starting a job of some size.

Conclusion

Quoting by real output (m²/day) rather than just billed hours is what lets you give deadlines that are met and explain to the client why a job takes the days it takes. Adding travel and waste management as their own items, not hidden costs, is what stops the margin being lost in the items that aren't seen.